Project category
Type D Instrument Financier
-
Estimated budget
81000000
Remove barriers for increased private sector involvement in small-scale (1MW-20MW) renewable energy power generation
Economic and financial criterias
-
i. Ability to produce electricity or heat or other forms of energy for productive use in small and medium scale agriculture, manufacturing and community services.
-
ii. Creation and maintenance of local jobs, whether for management positions and technical positions for assembly and maintenance of systems.
-
iii. Ability to stimulate economic diversification and growth (including local economic development)
Germany
-
iv. Economic benefits occurring within a reasonable period of time (in case a loan has been contracted rather than a grant)
RES Generation
-
v. Ability to raise funds to extend the project
31000000
-
vi. Ability to induce energy market transformation, innovation and cost reduction
-
vii. Accessibility at an affordable price for the majority of consumers
-
viii. Joint financing agreements (a factor demonstrating the willingness to carry out the project)
Social criterias
-
i. Empowerment of women
-
ii. Involvement of local stakeholders and civil society
-
iii. Proof of social acceptance and local ownership
Germany
-
iv. Improving equity in access to energy and promoting energy democracy
RES Generation
-
v. Respect for human rights and the rights of indigenous peoples
31000000
Environmental criteria
-
i. Impact on greenhouse gas emissions, including carbon dioxide and methane
-
ii. Impacts on local ecosystems and ecosystem services
-
iii. Impacts on land use and other land use impacts
Germany
-
iv. Recyclable nature of technologies exploiting renewable energies
RES Generation
-
v. Any other environmental criterion required by the national regulations / legislation in force
31000000
Institutional criteria Part 1
-
i. Compliance of the project with the priorities of the country concerned / region, without objection from other affected and affected countries, especially if the project has cross-border scope
-
ii. Synergy with ongoing / planned activities in the country (to avoid redundancies and incompatibilities during the implementation phase, while facilitating the healthy diversity of stakeholders and actions)
-
iii. Applicant's current capabilities, and track record demonstrating his ability to successfully complete the project, particularly with respect to his environmental and social duty of care
Germany
-
iv. Reproducibility
RES Generation
-
v. Durability
31000000
Institutional criteria Part 2
-
i. Detailed plan for mobilizing existing capacities
-
ii. Detailed plan, including resources needed, for the development of additional capabilities (to fill the gaps identified in subsection d.iv)
Technical criterias
-
i. Robust technical design
-
ii. Robustness and risk of failure / maintenance requirements
-
iii. Degree in which manufacture / assembly is carried out on national or African soil
Germany
-
iv. Capacity of the network (main and / or mini-grid) to absorb the production of power plants exploiting renewable energies and to absorb a variable energy yield
RES Generation
Project Follow Up
-
Lead financier
KfW Development Bank
-
Co-financier (if applicable)
-
Budget Total en Millions d’Euros
81.5
-
Equity in Millions of Euros
-
Financial Products
-
Project status
-
Technique Assistance in Millions Euros